Equipment

EP-300 power unit for industrial facilities

Purpose of the EP-300 power unit

The thermal power plant is designed to generate hot steam, electricity and desalted water for the technological needs of the Monomer plant in the Republic of Bashkortostan.

Composition

В состав тепловой электростанции входят два паровых котла с газо-импульсной очисткой поверхностей нагрева, суммарной производительностью 200 тонн острого пара в час (140 кгс/см?, 540°С), турбоагрегат электрический мощностью 18МВт, оборудование химводоподготовки.

Energobloq

WORKING

Construction of a turnkey thermal power plant, including construction and installation:

ASUTP

The created power unit is equipped with a distributed control system for the technological process of steam production. The thermal power plant ACSUTP is built on the technical means of Yokogawa.

All equipment located in the working area has an explosion-proof execution. The installation has permission from Rostekhnadzor for use in Russia, certificates of the State Standard of the Russian Federation.

TECHNICAL CHARACTERISTICS OF THERMAL POWER STATIONS

Parameters:
pressure-out 140 кгс/см?
Working steam temperature + 540 OH S
Productivity of each boiler 100 t/h
Parameters of the turbine:
Steam in 140 кгс/см?,
Operating temperature 540 OH S
Steam consumption 140 th
Steam pressure at release 16 кгс/см?
Design power at generator terminals 18 MW

The company performs delivery, commissioning and training of service personnel.
Delivery of equipment 12 months from the date of conclusion of the contract and prepayment.